Wednesday, June 29, 2011

Status as of 6/29/2011

After a couple of attempts to begin recirculating the processed water, it appears all the piping leaks have been fixed.  They are now injecting a mix of processed water and fresh water into the Unit 1, 2, and 3 reactors for cooling. 
Construction of the structure around the Unit 1 reactor building has begun.  A construction crane is now in place for lifting a steel framework which is being preassembled offsite.  Panels of one millimeter-thick polyester fiber panes will be attached to the frame.  The structure will be about 162 feet high and is expected to be completed by late September.