After a couple of attempts to begin recirculating the processed water, it appears all the piping leaks have been fixed. They are now injecting a mix of processed water and fresh water into the Unit 1, 2, and 3 reactors for cooling.
Construction of the structure around the Unit 1 reactor building has begun. A construction crane is now in place for lifting a steel framework which is being preassembled offsite. Panels of one millimeter-thick polyester fiber panes will be attached to the frame. The structure will be about 162 feet high and is expected to be completed by late September.